How to Navigate; PM Generator

This SOP outlines the steps for producing (generating) a PM work order.

Below are the guidelines.

For training purposes, the screenshots are in Aim Test.

The PM generator uses information from the PM template, the master asset profile, and the scheduled/ projected dates of the assets on the template asset screen to create pm work orders

Navigate to the Workdesk screen and select Preventive Maintenance.

https://fass-aim-app.uoregon.edu/fmax/screen/WORKDESK

 

pic1.png

Navigate to the Preventive Maintenance menu channel and select PM Generator.

 

pic2.png

Select new.

Screenshot 2024-07-17 130400.png

PM Generator: Aim defaults a system generated number. Do not change this number.

Screenshot 2024-07-17 130418.png

Enter a description such as a month-end date, shop, or pm information.  Example: MAY, 2025 AHU ANNUAL

pic5.png

Click on the calendar icon.

pic6.png

Add the end date.

This date is how far into the future the PM generator will produce PM work orders.

PM generation can be done monthly, weekly, daily, etc., based upon a department or organizational preference.

Recommended: generate through the month's end.  In the example, the month end is May 31, 2025.  

Important: This date is required to be in the future.

pic7.png

When creating a new PM generator record, nested PM defaults to No.

The work order generation process will create a separate work order for each frequency.

pic8.png

PM generation  “Filter By” defaults to Template Phase.

Do not change this.

pic9.png

Various filters can be chosen for PM generation based on the preference of a department or organization.

Important: Do not leave all filter options blank when generating PM work orders.

If no filters filter options are chosen, PM work orders across all templates in Aim will be generated.

This will overload Aim, and all departments or organizations' PM templates will be generated based on the end date chosen.

The most often used filter options are template, shop, asset type, and asset group.

Other filter options are asset, region, facility, property, and location.

Note: “Filter By” defaults to Asset. Do not change this.

pic10.png

In this example, the filter option will be Template.

Click on the magnifying icon on “Template”.

Screenshot 2024-07-17 144730.png

Select search.

pic12.png

Enter AHU.

Select execute.

pic13.png

Select the name of the template “AHU”.

pic14.png

Select save.

Screenshot 2024-07-17 144902.png

Note: The work orders have not yet been produced.

The final field indicates No.

This screen allows a preview for any edits or changes before generating work orders.

Click Generate.

Screenshot 2024-07-17 144953.png

A generating message will appear on the screen until the work order generation is complete.

pic17.png

The scheduled PM work orders have been generated/produced.

The work order numbers will be displayed under the Work Orders channel.

Note: if no problems have occurred, the “Final” field will indicate yes.

This is the completed successful PM Generator screen.

Screenshot 2024-07-17 145148.png

This is the completed PM work order.

 

Screenshot 2024-07-17 135906.png

Note that since the work order grouping was property by template, all five assets on the template asset phase in the PM Template now appear as five phases on one work order for the one property.

Each asset on the property by template is a phase on the work order.

Screenshot 2024-07-17 140430.png

This is the end of the SOP.

The following screens provide additional details to view within a PM Work order.

Screenshot 2024-07-17 150759.png

 Click account: The account set-up index pulls in the account setu setup on the master asset record.

 

Screenshot 2024-07-17 151552.png

Click back.

Screenshot 2024-07-17 151054.png

Click checkpoint measurements:

pic23.png

Note checkpoints from PM standard “AHU.”

Click back.

pic24.png

Checkpoint measurements that were required (requires data entry) are demonstrated below:

Click edit.

Screenshot 2024-07-17 150434.png

Click checkpoint measurements.

pic26.png

Red boxes require data.

Screenshot 2024-07-17 150318.png

Enter data as shown in the example.

Click on the magnifying icon for checkpoint 003.

pic28.png

Select yes.

pic29.png

Another example.

Click on calendar icons.

pic30.png

All red boxes are completed.

Click done.

pic31.png

Click save.

Screenshot 2024-07-17 150127.png

Click checkpoint measurements.

pic33.png

All required data is saved.

pic34.png

Click back.

Screenshot 2024-07-17 142906.png

This example demonstrates if one or more red boxes where required that require data have not been entered.

Checkpoint 003 has no data.

If the technician clicks done and tries to change the phase status to complete-pending review and then clicks save, the following red error code will appear: “checkpoint measurement required.”

 

Click cancel.

Screenshot 2024-07-17 145854.png

Click edit.

Click checkpoint measurements and complete data fields.

pic39.png

Then click done.

pic40.png

Then save.

Screenshot 2024-07-17 145617.png

Phase status is saved displays as compete-pending review.

Screenshot 2024-07-17 144003.png

End of additional detail screens.

 

...