Preventive Maintenance (PM) : PM Schedule Date Generator

Preventive Maintenance (PM) : PM Schedule Date Generator

How to Navigate; PM Schedule Date Generator

 

How to Navigate; PM Schedule Date Generator

 

This SOP outlines the steps for creating a PM Schedule Date Generator.

Below are the guidelines.

For training purposes, the screenshots are in Aim Test.

 

A PM Schedule Date Generator generates the scheduled or projected dates for the assets on the Template Asset Screen within the PM Template. 

 

Navigate to the WorkDesk screen and select Preventive Maintenance.

https://fass-aim-app.uoregon.edu/fmax/screen/WORKDESK

 

pic1.png

 

Select PM Schedule Date Generator.

 

pic2.png

 

Important note: Do not generate without entering some specific parameters or filters. Otherwise, if no parameters or filters are selected, dates will be generated for all PM templates in Aim. This can or will cause the load time to vary and be lengthy if specific parameters are not entered.

For specific generation needs, enter data in select fields as outlined below.

The asset block is used to filter the PM template assets, and projected dates will be generated based on the selected asset(s).

The shop block is used to filter by a specific shop on a template phase.

The location block is used to filter the assets installed in properties, which will have projected dates based on the region, facility, property, or location.

 

 

Screenshot 2024-07-17 123419.png

 

Select the calendar icon. The generation end date identifies how far into the future PM scheduled or projected dates are generated.

 

pic3.png

 

Note: even though the system generously allows future dates, the future date is typically chosen five years from the present or today’s date to the end of the selected month.

Select five years out from the present date.

Select the magnifying icon on the “Template field”

 

pic4.png

 

Click on search and enter the PM template name. In this example, AHU is chosen.

 

pic5.png

 

Select execute.

 

pic6.png

 

Click on AHU link.

 

pic7.png

 

Select Generate.

 

pic8.png

 

An informational box will appear to confirm the scheduled date projection generation is complete.

Select OK.

 

 

pic9.png

 

Confirm that the scheduled projected dates appear on the PM template.

Click on the horizontal three lines.

 

pic10.png

 

Select PM Template.

 

pic11.png

 

Click search.

 

pic12.png

 

Enter template “AHU”.

Select execute.

 

pic13.png

 

Click on AHU.

 

pic14.png

 

Click on Template Phase 001.

 

pic15.png

 

Select “Sequence 1” (an asset) on Template Asset.

 

pic16.png

 

Confirm the projected dates are visible. Note five years of projected dates.

Click back.

 

pic17.png

 

Then click back again to return to the PM Template screen.

 

pic18.png

 

Completed PM Schedule Date Generator.

 

pic19.png

 

The SOP PM Generator Preventive Maintenance (PM): PM Generator

 is referenced to accomplish the final outcome of producing PM work orders.

 

 

This is the end of SOP.

 

 